Anahata, Shivajinagar
by Raintree Developers LLP. Shivajinagar, Pune 411005. View on Google Maps
- Launched
- 2 years 3 months promised
- Possession date (MahaRERA)
- 1 year awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- 1 of 128% booked
Project facts
| 2 BHK | 2 |
|---|---|
| 3 BHK | 5 |
| 4 BHK | 5 |
| Total units | 12 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411005
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 3 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | October 2027 | March 2028 |
| Concrete structure (RCC) complete | 0% | 30% |
| Share of units booked | 8% | 12% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aparnali | August 2025 | December 2027 | 0% | 3 of 23 booked (13%) |
| Diya Samruddhi | October 2025 | December 2027 | 80% | 1 of 14 booked (7%) |
| Kamalini | October 2025 | December 2029 | 0% | Bookings not reported |
| Anand Dham | March 2025 | May 2028 | 60% | 3 of 8 booked (38%) |
| Sahavihar | February 2025 | April 2027 | 40% | Bookings not reported |
| Krupa | January 2025 | December 2028 | 20% | 1 of 9 booked (11%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 1 | |
| 100% | 0% | 0% | — | |
| 45% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Anahata (MahaRERA P52100080734) is a residential project by Raintree Developers LLP in Shivajinagar, Pune 411005. It was launched in July 2025. It has 12 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
1 of its 12 units is booked (8%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.