Skip to main content
← Back

Yasho Kalash, Kothrud

by Keyspace Buildcon LLP. Kothrud, Pune 411038. View on Google Maps

Launched
1 year 10 months originally promised
Possession date (MahaRERA)
1 year 1 month awayExtended by 1 year (originally November 2026). Why possession dates change
Concrete structure (RCC)
0%Early stage
Units booked
11 of 2741% booked

Project facts

1 BHK5
2 BHK8
3 BHK14
Total units27
Buildings1
Land0.3 acres
Rehab units11
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 411038

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 10 mths2 yrs 8 mths
Possession date extendedBy 1 year0 of 6
Possession date (MahaRERA)November 2027October 2027
Concrete structure (RCC) complete0%64%
Share of units booked41%19%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 9 months of the originally promised 1 year 10 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%11
95%0%0%11
0%0%0%11

"—" means MahaRERA shows no figure for that update.

About this project

Yasho Kalash (MahaRERA P52100078992) is a residential project by Keyspace Buildcon LLP in Kothrud, Pune 411038. It was launched in January 2025. It has 27 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2027, extended by 1 year from the original November 2026. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

11 of its 27 units are booked (41%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078992.Check it on MahaRERA (P52100078992)All projects in Kothrud