Skip to main content
← Back

24K Manor - Tower C and Shops, Pimple Nilakh

by Kolte-Patil Developers Limited. Pimple Nilakh, Pune 411027. View on Google Maps

Launched
4 years 4 months promised
Possession date (MahaRERA)
2 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
94%Mid-construction
Units booked
54 of 12045% booked

Project facts

3 BHK98
4 BHK7
5+ BHK4
Other units (shops, offices or not given by type)11
Total units120
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 34 → 54 · structure 25% → 94% · total units 68 → 120

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 8 months of the promised 4 years 4 months have passed
Concrete structure (RCC) 94% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 94%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 94%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%0%54
100%25%0%34
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

24K Manor - Tower C and Shops (MahaRERA P52100079296) is a residential project by Kolte-Patil Developers Limited in Pimple Nilakh, Pune 411027. It was launched in February 2025. It has 120 units in 1 building: 109 homes (3, 4 & 5+ BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

54 of its 120 units are booked (45%). Since the December 2025 update, 20 more units have been booked and the reported concrete structure (RCC) has gone from 25% to 94%.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079296.Check it on MahaRERA (P52100079296)All projects in Pimple Saudagar, Pimple Nilakh