Skip to main content
← Back

Unique Youtopia Phase IV, Kharadi

by Unique Associates. Kharadi, Pune 411014. View on Google Maps

Launched
3 years 6 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
33%Mid-constructionAverage across 2 buildings
Units booked
10 of 2135% booked
Price per sq ft (incl. balconies and terrace)
₹12,0002026 so far · 51 salesup 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK8
2 BHK160
3 BHK42
Other units (shops, offices or not given by type)3
Total units213
Buildings2
Land1.4 acres
Landowner share81
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 33% · total units 215 → 213

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
750 – 760 sq ft₹89 – 91 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹11,700 per sq ft10 sales
2026 so farup 3% on 2025₹12,000 per sq ft51 sales

Rate vs other Kharadi projects, 2026: similar

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 4 months of the promised 3 years 6 months have passed
Concrete structure (RCC) 33% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 33%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 33%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%10
80%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Unique Youtopia Phase IV (MahaRERA P52100080485) is a residential project by Unique Associates in Kharadi, Pune 411014. It was launched in June 2025. It has 213 units in 2 buildings: 210 homes (1, 2 & 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 33% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

10 of its 213 units are booked (5%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 33%. 80% of the 2026 (so far) sales we found here were at ₹12,000 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size, based on 51 registered sales. Buyers here paid a rate similar to other Kharadi projects in 2026. Most buyers paid ₹89–91 lakh for flats of 750–760 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080485.Check it on MahaRERA (P52100080485)All projects in Kharadi, Vadgaon Sheri, Viman Nagar