Skyrise Phase II, Wagholi

by Yashodha Buildcon. Wagholi, Pune 412207. View on Google Maps

Launched
2 years 10 months promised
Possession date (MahaRERA)
1 year 6 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
34 of 7247% booked
Price per sq ft (incl. balconies and terrace)
₹7,7002026 so far · 11 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK1
2 BHK48
3 BHK23
Total units72
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹7,700 per sq ft11 sales

Rate vs other Wagholi projects, 2026: about 35% lower

Compared with 5 similar projects in PIN 412207

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths4 yrs 4 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)April 2028December 2029
Concrete structure (RCC) complete0%0%
Share of units booked47%50%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 4 months of the promised 2 years 10 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%34
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Skyrise Phase II (MahaRERA P52100080706) is a residential project by Yashodha Buildcon in Wagholi, Pune 412207. It was launched in June 2025. It has 72 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

34 of its 72 units are booked (47%). 80% of the 2026 (so far) sales we found here were at ₹7,700 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 35% lower than at other Wagholi projects in 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080706.Check it on MahaRERA (P52100080706)All projects in Wagholi