Skip to main content
← Back

Sajan Siddhi D Wing, Shivane

Finishing stage

Final finishes 98% · completion not yet filed on MahaRERA

by Nemichand Bhandari Associates. Shivane, Pune 411023. View on Google Maps

Launched
3 months originally promised
Possession date (MahaRERA)
2 months awayExtended by 1 year (originally December 2025). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
6 of 3617% booked

Project facts

1 BHK36
Total units36
Buildings1
Land0.4 acres
Landowner share12
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 95% → 98%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 95%Jul 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%6
100%100%95%—

"—" means MahaRERA shows no figure for that update.

About this project

Sajan Siddhi D Wing (MahaRERA P52100080970) is a residential project by Nemichand Bhandari Associates in Shivane, Pune 411023. It was launched in September 2025. It has 36 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

6 of its 36 units are booked (17%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080970.Check it on MahaRERA (P52100080970)All projects in Shivane, Uttam Nagar, Kondhwe Dhawade