Landmarc, Hinjewadi

by Saheel Buildvision Private Limited. Hinjewadi, Pune 411057. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
3 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
340 of 47671% booked
Price per sq ft (incl. balconies and terrace)
₹10,5002026 so far · 40 salesup 6% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK341
3 BHK104
Other units (shops, offices or not given by type)31
Total units476
Buildings3
Land2.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 266 → 340

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
730 sq ft₹74 – 77 lakh
970 – 1,080 sq ft₹99 lakh – ₹1.16 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹9,900 per sq ft220 sales
2026 so farup 6% on 2025₹10,500 per sq ft40 sales

Rate vs other Maan projects, 2026: similar

Compared with 6 similar projects in PIN 411057

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs5 yrs 2 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)June 2030March 2031
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 4 months of the promised 5 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%340
0%0%0%266
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Landmarc (MahaRERA PM1260002500142) is a residential project by Saheel Buildvision Private Limited in Hinjewadi, Pune 411057. It was launched in June 2025. It has 476 units in 3 buildings: 445 homes (2 & 3 BHK) and 31 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

340 of its 476 units are booked (71%). Since the December 2025 update, 74 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹10,500 per sq ft or less (up 6% on 2025), counting balconies and terrace in the size, based on 40 registered sales. Buyers here paid a rate similar to other Maan projects in 2026. Most buyers paid ₹74–77 lakh for flats of 730 sq ft and ₹99 lakh–₹1.16 crore for 970–1,080 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002500142.Check it on MahaRERA (PM1260002500142)All projects in Wakad, Hinjewadi, Marunji