Gurukrupa 7 Avenue, Kiwale
by Gurukrupa Developers. Kiwale, Pune 412101. View on Google Maps
- Launched
- 3 years 7 months promised
- Possession date (MahaRERA)
- 2 years 5 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 3 buildings
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 10 |
|---|---|
| 2 BHK | 46 |
| 3 BHK | 10 |
| Other units (shops, offices or not given by type) | 3 |
| Total units | 69 |
| Buildings | 3 |
| Land | 1.2 acres |
| Landowner share | 13 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 412101
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 7 mths | 2 yrs 3 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | March 2029 | December 2027 |
| Concrete structure (RCC) complete | 0% | 60% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Lotus Florina | August 2025 | June 2026 | 100% | 2 of 98 booked (2%) |
| Sai Stella | August 2025 | December 2028 | 0% | 14 of 146 booked (10%) |
| Lenora | September 2025 | December 2029 | 0% | 7 of 97 booked (7%) |
| Aqua Life A Bldg | June 2025 | June 2027 | 100% | 34 of 66 booked (52%) |
| Onkar Greens | June 2025 | December 2027 | 40% | 20 of 55 booked (36%) |
| Sai Serenity | June 2025 | December 2026 | 80% | 9 of 52 booked (17%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 33% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Gurukrupa 7 Avenue (MahaRERA PM1260002500602) is a residential project by Gurukrupa Developers in Kiwale, Pune 412101. It was launched in August 2025. It has 69 units in 3 buildings: 66 homes (1, 2 & 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.