Lenora, Kiwale
by Sai Siddha Associates. Kiwale, Pune 412101. View on Google Maps
- Launched
- 4 years 3 months promised
- Possession date (MahaRERA)
- 3 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- 7 of 977% booked
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 54 |
| 3 BHK | 18 |
| Other units (shops, offices or not given by type) | 24 |
| Total units | 97 |
| Buildings | 2 |
| Land | 0.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 412101
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 3 mths | 3 yrs 11 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2029 | December 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Share of units booked | 7% | 14% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sheshachal Apartments | September 2025 | March 2029 | 0% | 16 of 46 booked (35%) |
| Sai Palladium | September 2025 | December 2029 | 0% | Bookings not reported |
| Sai Kripa | September 2025 | December 2030 | 0% | 1 of 44 booked (2%) |
| Millennium Amara Phase 2 | September 2025 | December 2029 | 3% | 38 of 144 booked (26%) |
| Gurukrupa 7 Avenue | August 2025 | March 2029 | 0% | Bookings not reported |
| Lotus Florina | August 2025 | June 2026 | 100% | 2 of 98 booked (2%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 30% | 0% | 0% | 7 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Lenora (MahaRERA PR1260002500833) is a residential project by Sai Siddha Associates in Kiwale, Pune 412101. It was launched in September 2025. It has 97 units in 2 buildings: 73 homes (1, 2 & 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation 30% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
7 of its 97 units are booked (7%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.