Ambrosia Studio, Baner

by Divyasparsh Realty LLP. Baner, Pune 411045. View on Google Maps

Launched
2 years 5 months promised
Possession date (MahaRERA)
1 year 5 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
2 of 524% booked
Price per sq ft (incl. balconies and terrace)
₹14,400studios · 2026 so far · 47 sales80% of the 2026 studio sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK47
Other units (shops, offices or not given by type)5
Total units52
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

Studios (under 450 sq ft)

₹14,400 per sq ft · studios · 2026 so far · 47 sales

80% of the 2026 studio sales we found were at this rate or less

2026 so far₹14,400 per sq ft47 sales

Sizes 170 – 200 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year of the promised 2 years 5 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Ambrosia Studio (MahaRERA PM1260002501271) is a residential project by Divyasparsh Realty LLP in Baner, Pune 411045. It was launched in October 2025. It has 52 units in 1 building: 47 homes (1 RK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

2 of its 52 units are booked (4%). Its studios (under 450 sq ft) sold at ₹14,400 per sq ft or less in 2026 (47 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.