Skip to main content
← Back

Kumar Prism Tower A, Keshavnagar

by Kumar Prism Realty LLP. Keshavnagar, Pune 411036. View on Google Maps

Launched
6 years promised
Possession date (MahaRERA)
5 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
Bookings not reported

Project facts

3 BHK42
4 BHK28
Other units (shops, offices or not given by type)12
Total units82
Buildings1
Land3.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 411036

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs4 yrs 7 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2031June 2030
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
10 months of the promised 6 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 20%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 20%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
20%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Kumar Prism Tower A (MahaRERA PM1260002501640) is a residential project by Kumar Prism Realty LLP in Keshavnagar, Pune 411036. It was launched in December 2025. It has 82 units in 1 building: 70 homes (3 & 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation 20% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002501640.Check it on MahaRERA (PM1260002501640)All projects in Mundhwa, Keshavnagar