Aqura Pride Wing A, Wadgaon Budruk
by Aqura Builder and Developer Private Limited. Wadgaon Budruk, Pune 411041. View on Google Maps
- Launched
- 2 years 5 months promised
- Possession date (MahaRERA)
- 1 year 7 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- 34 of 6453% booked
Project facts
| 3 BHK | 64 |
|---|---|
| Total units | 64 |
| Buildings | 1 |
| Land | 4.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411041
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 5 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | May 2028 | December 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Majestique Swapnangan Wing C, D and E | December 2025 | December 2030 | 0% | Bookings not reported |
| Sun Regalia | January 2026 | December 2030 | 0% | Bookings not reported |
| Alliance Sarthak | October 2025 | December 2029 | 0% | 5 of 45 booked (11%) |
| Yuvraj Residency | October 2025 | December 2027 | 85% | Bookings not reported |
| Bramhand One | April 2026 | July 2028 | 0% | Bookings not reported |
| NHC One | April 2026 | December 2029 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 34 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Aqura Pride Wing A (MahaRERA PM1260002501897) is a residential project by Aqura Builder and Developer Private Limited in Wadgaon Budruk, Pune 411041. It was launched in December 2025. It has 64 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is May 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
34 of its 64 units are booked (53%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.