Skip to main content
← Back

Aqura Pride, Wadgaon Budruk

by Aqura Builder and Developer Private Limited. Wadgaon Budruk, Pune 411041. View on Google Maps

Launched
3 years 10 months originally promised
Possession date (MahaRERA)
1 month agoExtended by 1 year (originally September 2025). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
103 of 13278% booked

Project facts

2 BHK105
3 BHK23
Other units (shops, offices or not given by type)4
Total units132
Buildings2
Land4.7 acres
Landowner share11
Complaints on MahaRERA (filed by or against the builder)6

Since Dec 2025: booked 104 → 103 · structure 95% → 100% · complaints 1 → 6

Share on WhatsApp

Compared with 4 similar projects in PIN 411041

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411041
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths4 yrs 6 mths
Possession date extendedBy 1 year3 of 4
Possession date (MahaRERA)September 2026December 2026
Concrete structure (RCC) complete100%100%
Share of units booked78%48%
Complaints on MahaRERA (filed by or against the builder)60

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 65%Dec 2024: Concrete structure (RCC) 38%Jun 2025: Concrete structure (RCC) 38%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%103
100%95%0%104
100%38%0%78
100%65%0%22
100%0%0%35

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Aqura Pride (MahaRERA P52100031863) is a residential project by Aqura Builder and Developer Private Limited in Wadgaon Budruk, Pune 411041. It was launched in November 2021. It has 132 units in 2 buildings: 128 homes (2 & 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2026, extended by 1 year from the original September 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

103 of its 132 units are booked (78%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 95% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031863.Check it on MahaRERA (P52100031863)All projects in Dhayari