Skip to main content
← Back

Yashwin Gateway, Ravet

by Kshipra Buildcon Private Limited. Ravet, Pune 412101. View on Google Maps

Launched
2 years 10 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
Bookings not reported

Project facts

1 BHK7
2 BHK41
Other units (shops, offices or not given by type)5
Total units53
Buildings1
Land0.4 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 412101

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths4 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2028June 2030
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
8 months of the promised 2 years 10 months have passed
Concrete structure (RCC) 0% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Yashwin Gateway (MahaRERA PM1260002502378) is a residential project by Kshipra Buildcon Private Limited in Ravet, Pune 412101. It was launched in February 2026, which makes it one of the newest launches in Kiwale, Ravet, Dehu Road. It has 53 units in 1 building: 48 homes (1 & 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Vilas Javdekar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA45
Completed without extending the possession date25
Completed after an extension, or lapsed1
Under construction19
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all Vilas Javdekar projects27 (19 of 45 projects)

See all Vilas Javdekar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002502378.Check it on MahaRERA (PM1260002502378)All projects in Kiwale, Ravet