Skip to main content
← Back

Arkaay Tower, Tathawade

by Rajwardhan Group. Tathawade, Pune 411033. View on Google Maps

Launched
6 years 10 months promised
Possession date (MahaRERA)
6 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
Bookings not reported

Project facts

1 BHK1
2 BHK5
Other units (shops, offices or not given by type)39
Total units45
Buildings3
Land1.2 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 411033

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 10 mths1 yr 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2032January 2028
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
8 months of the promised 6 years 10 months have passed
Concrete structure (RCC) 0% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Arkaay Tower (MahaRERA PM1260002502454) is a residential project by Rajwardhan Group in Tathawade, Pune 411033. It was launched in February 2026, which makes it one of the newest launches in Tathawade, Punawale, Nere, Jambhe. It has 45 units in 3 buildings: 6 homes (1 & 2 BHK) and 39 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2032, unchanged since launch. Construction, averaged across its 3 buildings: excavation 50% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002502454.Check it on MahaRERA (PM1260002502454)All projects in Tathawade, Punawale, Jambhe