Skylish Saai, Chinchwad
by Skylish Bluediamond Innfrracon. Chinchwad, Pune 411033. View on Google Maps
- Launched
- 1 year 9 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 2 BHK | 12 |
|---|---|
| 3 BHK | 4 |
| Total units | 16 |
| Buildings | 1 |
| Land | 0.2 acres |
| Rehab units | 9 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411033
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 9 mths | 3 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2027 | March 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashoka Prime | March 2026 | December 2030 | 0% | Bookings not reported |
| Avis Avante | March 2026 | January 2028 | 0% | Bookings not reported |
| The Orion | March 2026 | December 2028 | 0% | Bookings not reported |
| Nexus Skydale E Wing | March 2026 | June 2029 | 0% | Bookings not reported |
| Morya Residency | February 2026 | December 2026 | 100% | Bookings not reported |
| Arkaay Tower | February 2026 | December 2032 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Skylish Saai (MahaRERA PR1260002502976) is a residential project by Skylish Bluediamond Innfrracon in Chinchwad, Pune 411033. It was launched in March 2026, which makes it one of the newest launches in Tathawade, Punawale, Nere, Jambhe. It has 16 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.