Mizura Residences by Esbee, Manjari Budruk
by Esbee Greenspaces LLP. Manjari Budruk, Pune 412307. View on Google Maps
- Launched
- 4 years 3 months promised
- Possession date (MahaRERA)
- 3 years 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 3 buildings
- Units booked
- 72 of 30024% booked
- Price per sq ft (incl. balconies and terrace)
- ₹9,1002026 so far · 99 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 RK | 8 |
|---|---|
| 1 BHK | 20 |
| 2 BHK | 162 |
| 3 BHK | 108 |
| Other units (shops, offices or not given by type) | 2 |
| Total units | 300 |
| Buildings | 3 |
| Land | 1.6 acres |
| Reserved units | 23 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 750 sq ft | ₹65 – 69 lakh |
| 810 sq ft | ₹74 – 75 lakh |
| 1,050 – 1,060 sq ft | ₹88 – 98 lakh |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2026 so far | ₹9,100 per sq ft | 99 sales |
|---|
Rate vs other Manjari Budruk projects, 2026: about 5% higher
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 33% | 0% | 0% | 72 |
"—" means MahaRERA shows no figure for that update.
About this project
Mizura Residences by Esbee (MahaRERA PM1260002502579) is a residential project by Esbee Greenspaces LLP in Manjari Budruk, Pune 412307. It was launched in March 2026, which makes it one of the newest launches in Manjari, Shewalewadi. It has 300 units in 3 buildings: 298 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
72 of its 300 units are booked (24%). 80% of the 2026 (so far) sales we found here were at ₹9,100 per sq ft or less, counting balconies and terrace in the size, based on 99 registered sales. Buyers here paid a rate about 5% higher than at other Manjari Budruk projects in 2026. Most buyers paid ₹65–69 lakh for flats of 750 sq ft, ₹74–75 lakh for 810 sq ft and ₹88–98 lakh for 1,050–1,060 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.