Trio Sync, Tathawade
by Trio Lifespaces LLP. Tathawade, Pune 411033. View on Google Maps
- Launched
- 3 years promised
- Possession date (MahaRERA)
- 2 years 5 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
- Price per sq ft (incl. balconies and terrace)
- ₹12,600studios · 2026 so far · 54 sales80% of the 2026 studio sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 RK | 79 |
|---|---|
| Other units (shops, offices or not given by type) | 2 |
| Total units | 81 |
| Buildings | 1 |
| Land | 0.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
What buyers paid here
Studios (under 450 sq ft)
₹12,600 per sq ft · studios · 2026 so far · 54 sales
80% of the 2026 studio sales we found were at this rate or less
| 2026 so far | ₹12,600 per sq ft | 54 sales |
|---|
Sizes 190 – 220 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Trio Sync (MahaRERA PM1260002502951) is a residential project by Trio Lifespaces LLP in Tathawade, Pune 411033. It was launched in March 2026, which makes it one of the newest launches in Tathawade, Punawale, Nere, Jambhe. It has 81 units in 1 building: 79 homes (1 RK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet. Its studios (under 450 sq ft) sold at ₹12,600 per sq ft or less in 2026 (54 sales); studios are priced separately from flats.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.