Mangalam Starview, Kiwale

by Triyama Corp · Kiwale, Pune 412101 · Map

Launched
Jul 20264 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2031Extended by 4 mths
Concrete structure
0%Average of 3 towers
Booked
0 of 3960%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
207
3 BHK
155
Other units
34
Total units
396
Buildings
3
Land
4.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

From the architect's Form 1 filed with MahaRERA, latest filing Oct 2026. The last 4 updates per tower.

Last 4 updates, tower by tower
Building 1
UpdateExcavationStructureFinishes
Oct 20260%0%0%
Building 2
UpdateExcavationStructureFinishes
Oct 202635%0%0%
Building 3
UpdateExcavationStructureFinishes
Oct 202610%0%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
15%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹1.8 crore spent · latest estimate ₹75.7 crore · Oct 2026

Latest estimate ₹75.7 croreOct 2026: ₹1.8 crore1.8Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹1.8 crore

Compared with 5 similar projects in PIN 412101

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 412101
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths4 yrs 10 mths
Possession date extendedBy 4 mths0 of 5
Possession date (MahaRERA)Apr 2031Mar 2031
Concrete structure (RCC)0%0%
Units booked0%61%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Mangalam Starview by Triyama Corp is a 396-unit project in Kiwale, Pune 412101, launched in July 2026 with possession due in April 2031. 0 units booked out of total 396 units. Work on the concrete structure (RCC) has not started.

Read full summary

Mangalam Starview is a project by Triyama Corp in Kiwale, Pune 412101, registered with MahaRERA as PM1260002601151. It was launched in July 2026. It has 396 units in 3 buildings: 362 homes (2 and 3 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2031, extended by 4 months from the original December 2030. Construction, averaged across its 3 towers: excavation 15% complete, structure (RCC) not started, final finishes not started.

0 units booked out of total 396 units (0%).