by Madhur Shelters · Parvati, Pune 411009 · Map

Launched
Jul 20262 yrs 6 mths originally promised
Possession (MahaRERA)
May 2029Extended by 4 mths
Concrete structure
0%Early stage
Booked
12 of 2157%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
3
2 BHK
6
3 BHK
5
Other units
7
Total units
21
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Rehab units
11

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building
UpdateStructureFinishes
Oct 20260%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹1.5 crore spent · latest estimate ₹9.0 crore · Oct 2026

Latest estimate ₹9.0 croreOct 2026: ₹1.5 crore1.5Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹1.5 crore

Compared with 6 similar projects in PIN 411009

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411009
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths2 yrs 8 mths
Possession date extendedBy 4 mths1 of 6
Possession date (MahaRERA)May 2029Feb 2029
Concrete structure (RCC)0%0%
Units booked57%68%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Snehalkunj by Madhur Shelters is a 21-unit project in Parvati, Pune 411009, launched in July 2026 with possession due in May 2029. 12 units booked out of total 21 units. Work on the concrete structure (RCC) has not started.

Read full summary

Snehalkunj is a project by Madhur Shelters in Parvati, Pune 411009, registered with MahaRERA as PM1260002601176. It was launched in July 2026. It has 21 units in 1 building: 14 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2029, extended by 4 months from the original January 2029. Construction: excavation complete, structure (RCC) not started, final finishes not started.

12 units booked out of total 21 units (57%).