by M/s SHREERAM HOUSING · Parvati, Pune 411009 · Map

Launched
Aug 20262 yrs 5 mths promised
Possession (MahaRERA)
Jan 2029Not extended
Concrete structure
0%Early stage
Booked
0 of 60%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
2
3 BHK
4
Total units
6
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building A
UpdateStructureFinishes
Oct 20260%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹33 lakh spent · latest estimate ₹2.9 crore · Oct 2026

Latest estimate ₹2.9 croreOct 2026: ₹33 lakh0.3Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹33 lakh

Compared with 5 similar projects in PIN 411009

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411009
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths2 yrs 6 mths
Possession date extendedNo2 of 5
Possession date (MahaRERA)Jan 2029May 2029
Concrete structure (RCC)0%0%
Units booked0%70%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Satyam by M/s SHREERAM HOUSING is a 6-unit project in Parvati, Pune 411009, launched in August 2026 with possession due in January 2029. 0 units booked out of total 6 units. Work on the concrete structure (RCC) has not started.

Read full summary

Satyam is a project by M/s SHREERAM HOUSING in Parvati, Pune 411009, registered with MahaRERA as PR1260002601550. It was launched in August 2026. It has 6 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of total 6 units (0%).