Austin Ira, Mamurdi
by Yashada Shravani Group · Mamurdi, Pune 412101 · Map
- Launched
- Aug 20265 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2031Not extended
- Concrete structure
- 0%Average of 4 towers
- Booked
- 19 of 15612%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 61
- 2 BHK
- 39
- 3 BHK
- 30
- Other units
- 26
- Total units
- 156
- Buildings
- 4
- Land
- 3.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
From the architect's Form 1 filed with MahaRERA, latest filing Oct 2026. The last 4 updates per tower.
Last 4 updates, tower by tower
| Update | Excavation | Structure | Finishes |
|---|---|---|---|
| Oct 2026 | 30% | 0% | 0% |
| Update | Excavation | Structure | Finishes |
|---|---|---|---|
| Oct 2026 | 30% | 0% | 0% |
| Update | Excavation | Structure | Finishes |
|---|---|---|---|
| Oct 2026 | 30% | 0% | 0% |
| Update | Excavation | Structure | Finishes |
|---|---|---|---|
| Oct 2026 | 0% | 0% | 0% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 23% | 0% | 0% | 19 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹6.4 crore spent · latest estimate ₹270.6 crore · Oct 2026
Spent at each update
| Update | Spent |
|---|---|
| Oct 2026 | ₹6.4 crore |
Compared with 6 similar projects in PIN 412101
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2031 | Jan 2031 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked | 12% | 5% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shaligram The Mile, Ravet
- iLife 6, Ravet
- Sukhwani Palmera Reserves Phase I, Kiwale
- Miracle - II, Kiwale
- Imperial Residency, Ravet
- Sonigara Richmont, Ravet
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shaligram The Mile | August 2026 | December 2031 | 0% | 34 units booked out of total 77 units |
| iLife 6 | August 2026 | December 2030 | 0% | 0 units booked out of total 80 units |
| Sukhwani Palmera Reserves Phase I | August 2026 | March 2031 | 0% | 0 units booked out of total 243 units |
| Miracle - II | September 2026 | December 2029 | 18% | 18 units booked out of total 167 units |
| Imperial Residency | September 2026 | June 2029 | 0% | 0 units booked out of total 72 units |
| Sonigara Richmont | October 2026 | December 2032 | 0% | 66 units booked out of total 168 units |
About this project
Austin Ira by Yashada Shravani Group is a 156-unit project in Mamurdi, Pune 412101, launched in August 2026 with possession due in December 2031. 19 units booked out of total 156 units. Work on the concrete structure (RCC) has not started.
Read full summary
Austin Ira is a project by Yashada Shravani Group in Mamurdi, Pune 412101, registered with MahaRERA as PM1260002601545. It was launched in August 2026. It has 156 units in 4 buildings: 130 homes (1, 2 and 3 BHK) and 26 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2031, unchanged since launch. Construction, averaged across its 4 towers: excavation 23% complete, structure (RCC) not started, final finishes not started.
19 units booked out of total 156 units (12%).
Yashada's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 7,335 |
| Completed without extending the possession date | 22 |
| Completed after an extension | 2 |
| Lapsed | 3 |
| Under construction | 11 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 2 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Yashada projects | 11 (8 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.