Divine Reves, Wing A, Wakad

by Divine Homes Developers. Wakad, Pune 411057. View on Google Maps

Launched
3 years 5 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
2 of 395% booked
Price per sq ft (incl. balconies and terrace)
₹8,9002026 so far · 17 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK23
3 BHK11
Other units (shops, offices or not given by type)5
Total units39
Buildings1
Land0.7 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
800 – 850 sq ft₹66 – 76 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹8,900 per sq ft17 sales

Rate vs other Wakad projects, 2026: about 20% lower

Compared with 5 similar projects in PIN 411057

Projects with 10–70 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 5 mths3 yrs 7 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)December 2028March 2029
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 3 months of the promised 3 years 5 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Divine Reves, Wing A (MahaRERA PM1261012500390) is a residential project by Divine Homes Developers in Wakad, Pune 411057. It was launched in July 2025. It has 39 units in 1 building: 34 homes (2 & 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

2 of its 39 units are booked (5%). 80% of the 2026 (so far) sales we found here were at ₹8,900 per sq ft or less, counting balconies and terrace in the size, based on 17 registered sales. Buyers here paid a rate about 20% lower than at other Wakad projects in 2026. Most buyers paid ₹66–76 lakh for flats of 800–850 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1261012500390.Check it on MahaRERA (PM1261012500390)All projects in Wakad, Hinjewadi, Marunji