Skip to main content
← Back

Elixir - Phase I, Kondhwa Khurd

by Kolte-Patil Developers Limited. Kondhwa Khurd, Pune 411048. View on Google Maps

Launched
4 years 10 months promised
Possession date (MahaRERA)
3 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
Bookings not reported

Project facts

2 BHK8
3 BHK156
4 BHK54
Total units218
Buildings2
Land5.7 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 411048

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 10 mths5 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2030February 2031
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 2 months of the promised 4 years 10 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 45%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 45%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
45%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Elixir - Phase I (MahaRERA PR1261012500503) is a residential project by Kolte-Patil Developers Limited in Kondhwa Khurd, Pune 411048. It was launched in August 2025. It has 218 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2030, unchanged since launch. Construction, averaged across its 2 buildings: excavation 45% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1261012500503.Check it on MahaRERA (PR1261012500503)All projects in Kondhwa, Yewalewadi, Pisoli