Spenta Nest, Dadar East
by Shubh Enterprises · Dadar East, Mumbai 400014 · Map
- Launched
- Sep 201711 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 28
- Total units
- 28
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | – | |
| 100% | 100% | 50% | – | |
| 100% | 100% | 50% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400014
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 11 yrs 3 mths | 3 yrs 1 mth |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Apr 2023 |
| Concrete structure (RCC) | 100% | 90% |
| Units booked | – | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Govind Niwas, Dadar East
- 63 Elegance, Dadar East
- LS Laxmi Sadan, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Govind Niwas | September 2017 | April 2023 | 0% | 9 units booked out of total 15 units |
| 63 Elegance | August 2017 | June 2026 | 100% | 6 units booked out of 12 units for sale |
| LS Laxmi Sadan | August 2017 | September 2020 | 90% | 10 units booked out of total 12 units |
About this project
Spenta Nest by Shubh Enterprises (Spenta) is a 28-unit project in Dadar East, Mumbai 400014, launched in September 2017 with possession due in December 2028. The concrete structure (RCC) is complete.
Read full summary
Spenta Nest is a project by Shubh Enterprises in Dadar East, Mumbai 400014, registered with MahaRERA as P51900012560. It was launched in September 2017. It has 28 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
Spenta's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 1,369 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 2 |
| Lapsed | 0 |
| Under construction | 7 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Spenta projects | 43 (6 of 10 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.