Skip to main content

Spenta Nest, Dadar East

by Shubh Enterprises · Dadar East, Mumbai 400014 · Map

Launched
Sep 201711 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
28
Total units
28
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%–
100%100%50%–
100%100%50%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400014

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)11 yrs 3 mths3 yrs 1 mth
Possession date extendedNo2 of 3
Possession date (MahaRERA)Dec 2028Apr 2023
Concrete structure (RCC)100%90%
Units booked–60%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Spenta Nest by Shubh Enterprises (Spenta) is a 28-unit project in Dadar East, Mumbai 400014, launched in September 2017 with possession due in December 2028. The concrete structure (RCC) is complete.

Read full summary

Spenta Nest is a project by Shubh Enterprises in Dadar East, Mumbai 400014, registered with MahaRERA as P51900012560. It was launched in September 2017. It has 28 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

Spenta's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA10
Total units across these projects1,369
Completed without extending the possession date1
Completed after an extension2
Lapsed0
Under construction7
Possession date extended on the builder's application7
Typical time from launch to 100% structure7 years 5 months
MahaRERA complaints (filed by or against the builder), all Spenta projects43 (6 of 10 projects)

See all Spenta projects →