Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey, Santacruz East
Lapsed
by Maharashtra Housing And Area Development Authority · Santacruz East, Mumbai 400055 · Map
- Launched
- Jun 20171 yr originally promised
- Possession (MahaRERA)
- Oct 2020Extended by 2 yrs 4 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 63 of 7288%
- Buildings
- 10.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 72
- Total units
- 72
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 63 | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | 63 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400055
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr | 3 yrs 9 mths |
| Possession date extended | By 2 yrs 4 mths | 2 of 3 |
| Possession date (MahaRERA) | Oct 2020 | Jun 2023 |
| Concrete structure (RCC) | 100% | 97% |
| MahaRERA complaints (filed by or against the builder) | 0 | 3 |
The 3 projects
- Bluemoon Annexe, Santacruz East
- Rizvi Utopia, Santacruz East
- Sagar Avenue II EF, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bluemoon Annexe | August 2017 | December 2025 | 92% | 59 units booked out of 71 units for sale |
| Rizvi Utopia | September 2017 | June 2022 | 97% | – |
| Sagar Avenue II EF | September 2017 | June 2023 | 100% | – |
About this project
Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey by Maharashtra Housing And Area Development Authority is a 72-unit project in Santacruz East, Mumbai 400055, launched in June 2017; its MahaRERA registration has lapsed. 63 units booked out of total 72 units. The concrete structure (RCC) is complete.
Read full summary
Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey is a project by Maharashtra Housing And Area Development Authority in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800000041. It was launched in June 2017. It has 72 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in October 2020, after an extension of 2 years 4 months from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
63 units booked out of total 72 units (88%).