Skip to main content

Bluemoon Annexe, Santacruz East

Lapsed

by Mudassar Builders & Developers · Santacruz East, Mumbai 400055 · Map

Launched
Aug 20171 yr 1 mth originally promised
Possession (MahaRERA)
Dec 2025Extended by 7 yrs 3 mthsWhat does Lapsed mean?
Concrete structure
92%Mid-construction
Booked (free sale)
59 of 7183% · 60 rehab units
Buildings
30.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale59 booked out of 71 units

Rehab60 units for existing members

Land-owner share4 units, not for sale

Total 135 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
58
1 BHK
4
2 BHK
6
3 BHK
9
Other units
58
Total units
135
Buildings
3
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
71
Rehab units
60
Land-owner share (not for sale)
4
Reserved units
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 92%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 67%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 92%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%60%59
100%92%60%59
100%92%60%–
100%92%67%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400055

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400055
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 1 mth4 yrs 9 mths
Possession date extendedBy 7 yrs 3 mths5 of 6
Possession date (MahaRERA)Dec 2025Jan 2024
Concrete structure (RCC)92%100%
Units booked (free sale)83%82%
MahaRERA complaints (filed by or against the builder)02

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Bluemoon Annexe by Mudassar Builders & Developers is a 135-unit SRA-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2017; its MahaRERA registration has lapsed. 59 units booked out of 71 units for sale. The concrete structure (RCC) is 92% complete.

Read full summary

Bluemoon Annexe is an SRA-sanctioned project by Mudassar Builders & Developers in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800003318. It was launched in August 2017. It has 135 units in 3 buildings: 77 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 58 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 135 units, 71 are for sale, 60 are rehab units for existing members and 4 are the land-owner's share, not for sale.

Possession was due in December 2025, after an extension of 7 years 3 months from the original September 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 92% complete, final finishes 60% complete.

59 units booked out of 71 units for sale (83%).