Rizvi Utopia, Santacruz East
Lapsed
by Rizvi Estates & Hotels Pvt Ltd · Santacruz East, Mumbai 400055 · Map
- Launched
- Sep 20173 yrs 9 mths originally promised
- Possession (MahaRERA)
- Jun 2022Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 97%Mid-construction
- Booked
- –
- Buildings
- 31.1 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 62
- 3 BHK
- 33
- Other units
- 6
- Total units
- 102
- Buildings
- 3
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 92% | – | |
| 100% | 97% | 92% | – | |
| 100% | 97% | 92% | 91 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400055
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 5 yrs 9 mths |
| Possession date extended | By 1 yr | 3 of 5 |
| Possession date (MahaRERA) | Jun 2022 | Jun 2023 |
| Concrete structure (RCC) | 97% | 100% |
| Units booked | – | 85% |
| MahaRERA complaints (filed by or against the builder) | 5 | 0 |
The 5 projects
- Sagar Avenue II EF, Santacruz East
- Sagar Avenue II G, Santacruz East
- Bluemoon Annexe, Santacruz East
- Ekta Sra Chs, Santacruz East
- Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sagar Avenue II EF | September 2017 | June 2023 | 100% | – |
| Sagar Avenue II G | September 2017 | June 2023 | 57% | – |
| Bluemoon Annexe | August 2017 | December 2025 | 92% | 59 units booked out of 71 units for sale |
| Ekta Sra Chs | August 2017 | July 2024 | 100% | 23 units booked out of 27 units for sale |
| Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey | June 2017 | October 2020 | 100% | 63 units booked out of total 72 units |
About this project
Rizvi Utopia by Rizvi Estates & Hotels Pvt Ltd is a 102-unit project in Santacruz East, Mumbai 400055, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 97% complete.
Read full summary
Rizvi Utopia is a project by Rizvi Estates & Hotels Pvt Ltd in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800012249. It was launched in September 2017. It has 102 units in 3 buildings: 96 homes (1, 2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2022, after an extension of 1 year from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 97% complete, final finishes 92% complete.