Montana, Mulund West

by Lohitka Properties LLP · Mulund West, Mumbai 400080 · Map

Launched
Jul 2017First of 3 phases
Possession (MahaRERA)
Dec 2026Extended in 1 of 3 phases
Concrete structure
100%Weighted across 3 phases
Booked
–
Buildings
32.2 acres
MahaRERA complaints
24Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
561
3 BHK
403
4 BHK
43
Total units
1,007
Buildings
3
Land
2.2 acres
Phases
3
MahaRERA complaints
24

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Montana Phase - 1
Completed
P51800000735300100%–
Montana Phase - 3
Ready to move
P51800017754332100%99%
Montana Phase - 4
Nearing possession
P51800026393375100%97%
Show updates by phase

Montana Phase - 1 (P51800000735)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%298

"–" means MahaRERA shows no figure for that update.

Montana Phase - 3 (P51800017754)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%329
100%100%100%329
100%100%70%325
100%74%0%317

"–" means MahaRERA shows no figure for that update.

Montana Phase - 4 (P51800026393)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%364
100%100%30%364
100%100%0%361
100%0%0%346

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 54%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 30%Dec 2025: Final finishes 53%Jul 2026: Final finishes 74%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

How to read construction stages

Compared with 4 similar projects in PIN 400080

Projects with 500–2,100 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 3 mths5 yrs 3 mths
Possession date extendedYes2 of 4
Possession date (MahaRERA)Dec 2026Jan 2027
Concrete structure (RCC)100%96%
MahaRERA complaints (filed by or against the builder)2429

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Montana by Lohitka Properties LLP is a 1,007-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 3 phases, with possession due in December 2026. The concrete structure (RCC) is complete.

Read full summary

Montana is a BMC-sanctioned project by Lohitka Properties LLP in Mulund West, Mumbai 400080, registered with MahaRERA as 3 phases (P51800000735, P51800017754, P51800026393). The first phase was launched in July 2017. Together the phases have 1,007 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is completed.

The registered possession date is December 2026; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 80% complete. All 3 phases have their structure complete.