The Sanctuary, Mulund West

by Runwal Construction Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Sep 2017First of 4 phases
Possession (MahaRERA)
Jan 2027 – Mar 2027Extended in 2 of 4 phases
Concrete structure
94%Weighted across 4 phases
Booked
891 of 1,79750%
Buildings
86 acres
MahaRERA complaints
64Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
2 BHK
1,042
3 BHK
684
4 BHK
69
Total units
1,797
Buildings
8
Land
6 acres
Phases
4
MahaRERA complaints
64

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Sanctuary
Completed
P518000126211,005–17%
The Sanctuary - Tower 4
Ready to move
P51800025926264100%99%
The Sanctuary - Tower 5
Ready to move
P51800029440264100%87%
The Sanctuary - Tower 2
Mid-construction
P5180003253826465%88%
Show updates by phase

The Sanctuary (P51800012621)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%54%167
100%98%54%–
100%98%54%–
100%91%41%167

"–" means MahaRERA shows no figure for that update.

The Sanctuary - Tower 4 (P51800025926)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%263
100%83%0%261
100%83%0%–
100%83%0%229

"–" means MahaRERA shows no figure for that update.

The Sanctuary - Tower 5 (P51800029440)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%230
100%96%0%–
100%96%0%–
100%96%0%189

"–" means MahaRERA shows no figure for that update.

The Sanctuary - Tower 2 (P51800032538)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%0%231
100%65%0%185
100%65%0%185
100%65%0%120

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services59%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 91%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 23%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 59%Excavation 100%Concrete structure (RCC) 94%Final finishes 59%

How to read construction stages

Compared with 3 similar projects in PIN 400080

Projects with 800–3,600 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 6 mths5 yrs 6 mths
Possession date extendedYes1 of 3
Possession date (MahaRERA)Jan 2027 – Mar 2027Dec 2026
Concrete structure (RCC)94%100%
MahaRERA complaints (filed by or against the builder)6424

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

The Sanctuary by Runwal Construction Private Limited is a 1,797-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 4 phases, with possession dates from January 2027 to March 2027. 891 units booked out of total 1,797 units. The concrete structure (RCC) is 94% complete.

Read full summary

The Sanctuary is a BMC-sanctioned project by Runwal Construction Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as 4 phases (P51800012621, P51800025926, P51800029440, P51800032538). The first phase was launched in September 2017. Together the phases have 1,797 units in 8 buildings, with 1 RK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is completed.

The phases' registered possession dates run from January 2027 to March 2027; 2 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 94% complete and final finishes 59% complete. 2 of the 4 phases have their structure complete.

891 units booked out of total 1,797 units (50%).

Runwal's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA46
Total units across these projects14,623
Completed without extending the possession date10
Completed after an extension5
Lapsed5
Under construction26
Possession date extended on the builder's application16
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Runwal projects343 (35 of 46 projects)