The Sanctuary, Mulund West
by Runwal Construction Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Sep 2017First of 4 phases
- Possession (MahaRERA)
- Jan 2027 – Mar 2027Extended in 2 of 4 phases
- Concrete structure
- 94%Weighted across 4 phases
- Booked
- 891 of 1,79750%
- Buildings
- 86 acres
- MahaRERA complaints
- 64Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 2 BHK
- 1,042
- 3 BHK
- 684
- 4 BHK
- 69
- Total units
- 1,797
- Buildings
- 8
- Land
- 6 acres
- Phases
- 4
- MahaRERA complaints
- 64
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| The Sanctuary Completed | P51800012621 | 1,005 | – | 17% | |
| The Sanctuary - Tower 4 Ready to move | P51800025926 | 264 | 100% | 99% | |
| The Sanctuary - Tower 5 Ready to move | P51800029440 | 264 | 100% | 87% | |
| The Sanctuary - Tower 2 Mid-construction | P51800032538 | 264 | 65% | 88% |
Show updates by phase
The Sanctuary (P51800012621)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 54% | 167 | |
| 100% | 98% | 54% | – | |
| 100% | 98% | 54% | – | |
| 100% | 91% | 41% | 167 |
"–" means MahaRERA shows no figure for that update.
The Sanctuary - Tower 4 (P51800025926)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 263 | |
| 100% | 83% | 0% | 261 | |
| 100% | 83% | 0% | – | |
| 100% | 83% | 0% | 229 |
"–" means MahaRERA shows no figure for that update.
The Sanctuary - Tower 5 (P51800029440)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 230 | |
| 100% | 96% | 0% | – | |
| 100% | 96% | 0% | – | |
| 100% | 96% | 0% | 189 |
"–" means MahaRERA shows no figure for that update.
The Sanctuary - Tower 2 (P51800032538)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 65% | 0% | 231 | |
| 100% | 65% | 0% | 185 | |
| 100% | 65% | 0% | 185 | |
| 100% | 65% | 0% | 120 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400080
Projects with 800–3,600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 6 mths | 5 yrs 6 mths |
| Possession date extended | Yes | 1 of 3 |
| Possession date (MahaRERA) | Jan 2027 – Mar 2027 | Dec 2026 |
| Concrete structure (RCC) | 94% | 100% |
| MahaRERA complaints (filed by or against the builder) | 64 | 24 |
The 3 projects
- Piramal Revanta, Mulund West
- Atmosphere, Mulund West
- Montana, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Piramal Revanta | August 2017 | Nov 2028 – Jul 2030 | 97% | – |
| Atmosphere | July 2017 | Dec 2026 | 100% | – |
| Montana | July 2017 | Dec 2026 | 100% | – |
About this project
The Sanctuary by Runwal Construction Private Limited is a 1,797-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 4 phases, with possession dates from January 2027 to March 2027. 891 units booked out of total 1,797 units. The concrete structure (RCC) is 94% complete.
Read full summary
The Sanctuary is a BMC-sanctioned project by Runwal Construction Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as 4 phases (P51800012621, P51800025926, P51800029440, P51800032538). The first phase was launched in September 2017. Together the phases have 1,797 units in 8 buildings, with 1 RK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is completed.
The phases' registered possession dates run from January 2027 to March 2027; 2 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 94% complete and final finishes 59% complete. 2 of the 4 phases have their structure complete.
891 units booked out of total 1,797 units (50%).
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.