Ajmera Treon, Wadala East
Lapsed
by Ajmera Realty & Infra India Ltd · Wadala East, Mumbai 400037 · Map
- Launched
- Jul 20177 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 55%Mid-construction
- Booked
- –
- Buildings
- 227.6 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 8
- 1 BHK
- 2
- 2 BHK
- 116
- 3 BHK
- 68
- 4 BHK
- 68
- Other units
- 11
- Total units
- 273
- Buildings
- 2
- Land
- 27.6 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 50% | – | |
| 100% | 55% | 50% | – | |
| 100% | 55% | 50% | 195 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400037
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 5 mths | 6 yrs 3 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2024 | Dec 2023 |
| Concrete structure (RCC) | 55% | 18% |
| Units booked | – | 39% |
| MahaRERA complaints (filed by or against the builder) | 3 | 1 |
The 3 projects
- Maaria Annexe, Wadala East
- Wadala, Wadala East
- Zeus Residency Sale Bldg No.6, Wadala East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Maaria Annexe | August 2017 | December 2029 | 85% | 72 units booked out of total 159 units |
| Wadala | August 2017 | December 2023 | 0% | 52 units booked out of total 133 units |
| Zeus Residency Sale Bldg No.6 | September 2017 | December 2023 | 18% | 35 units booked out of total 222 units |
About this project
Ajmera Treon by Ajmera Realty & Infra India Ltd is a 273-unit BMC-sanctioned project in Wadala East, Mumbai 400037, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 55% complete.
Read full summary
Ajmera Treon is a BMC-sanctioned project by Ajmera Realty & Infra India Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as P51800000776. It was launched in July 2017. It has 273 units in 2 buildings: 262 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 55% complete, final finishes 50% complete.
Ajmera's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 23 |
|---|---|
| Total units across these projects | 4,563 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 4 years 11 months |
| MahaRERA complaints (filed by or against the builder), all Ajmera projects | 15 (9 of 23 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.