Ajmera Treon, Wadala East

Lapsed

by Ajmera Realty & Infra India Ltd · Wadala East, Mumbai 400037 · Map

Launched
Jul 20177 yrs 5 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
55%Mid-construction
Booked
–
Buildings
227.6 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
8
1 BHK
2
2 BHK
116
3 BHK
68
4 BHK
68
Other units
11
Total units
273
Buildings
2
Land
27.6 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)55%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 55%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 55%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%55%50%–
100%55%50%–
100%55%50%195

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400037

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400037
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 5 mths6 yrs 3 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2024Dec 2023
Concrete structure (RCC)55%18%
Units booked–39%
MahaRERA complaints (filed by or against the builder)31

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Ajmera Treon by Ajmera Realty & Infra India Ltd is a 273-unit BMC-sanctioned project in Wadala East, Mumbai 400037, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 55% complete.

Read full summary

Ajmera Treon is a BMC-sanctioned project by Ajmera Realty & Infra India Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as P51800000776. It was launched in July 2017. It has 273 units in 2 buildings: 262 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 55% complete, final finishes 50% complete.

Ajmera's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects4,563
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)

See all Ajmera projects →