Sankalp Heights 1-22, Malad West
by Status Construction Pvt Ltd · Malad West, Mumbai 400095 · Map
- Launched
- Jul 20175 yrs 11 mths originally promised
- Possession (MahaRERA)
- Jun 2024Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 40
- 3 BHK
- 20
- Total units
- 60
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | – | |
| 100% | 100% | 75% | – | |
| 100% | 100% | 75% | 24 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400095
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 11 mths | 6 yrs 4 mths |
| Possession date extended | By 1 yr | 3 of 3 |
| Possession date (MahaRERA) | Jun 2024 | Dec 2026 |
| Concrete structure (RCC) | 100% | 85% |
| Units booked | – | 30% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 3 projects
Other phases of this project are not included in the similar projects.
About this project
Sankalp Heights 1-22 by Status Construction Pvt Ltd is a 60-unit project in Malad West, Mumbai 400095, launched in July 2017 with possession due in June 2024. The concrete structure (RCC) is complete.
Read full summary
Sankalp Heights 1-22 is a project by Status Construction Pvt Ltd in Malad West, Mumbai 400095, registered with MahaRERA as P51800002085. It was launched in July 2017. It has 60 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in June 2024, after an extension of 1 year from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.