Bay Vue, Malad West

by H And Y Realities Privae Limited · Malad West, Mumbai 400095 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 4 yrs
Concrete structure
100%Nearing possession
Booked (free sale)
56 of 11350%
Buildings
11.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale56 booked out of 113 units

Land-owner share27 units, not for sale

Total 140 units. Land-owner units are not for sale.

Project facts

1 BHK
38
2 BHK
61
3 BHK
34
Other units
7
Total units
140
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
113
Land-owner share (not for sale)
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services2%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 80%Oct 2026: Final finishes 2%Excavation 100%Concrete structure (RCC) 100%Final finishes 2%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%2%56
100%100%80%46
100%0%0%44
100%0%0%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400095

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400095
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths6 yrs 4 mths
Possession date extendedBy 4 yrs3 of 3
Possession date (MahaRERA)Dec 2026Dec 2025
Concrete structure (RCC)100%85%
MahaRERA complaints (filed by or against the builder)02

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Bay Vue by H And Y Realities Privae Limited is a 140-unit SRA-sanctioned project in Malad West, Mumbai 400095, launched in August 2017 with possession due in December 2026. 56 units booked out of 113 units for sale. The concrete structure (RCC) is complete.

Read full summary

Bay Vue is an SRA-sanctioned project by H And Y Realities Privae Limited in Malad West, Mumbai 400095, registered with MahaRERA as P51800009514. It was launched in August 2017. It has 140 units in 1 building: 133 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 113 are for sale and 27 are the land-owner's share, not for sale.

Its registered possession date is December 2026, extended by 4 years from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 2% complete.

56 units booked out of 113 units for sale (50%). Since the July 2026 update, 10 more units have been booked and the possession date has moved from December 2025 to December 2026.