Scorpio, Malad West
by Jasani Realty PvtLtd · Malad West, Mumbai 400095 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrs
- Concrete structure
- 85%Mid-construction
- Booked
- 42 of 13930%
- Buildings
- 10.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 84
- 3 BHK
- 42
- Other units
- 13
- Total units
- 139
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 15% | 42 | |
| 95% | 78% | 15% | 42 | |
| 95% | 39% | 0% | 38 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400095
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 5 yrs 11 mths |
| Possession date extended | By 2 yrs | 3 of 3 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2026 |
| Concrete structure (RCC) | 85% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 3 projects
- Bay Vue, Malad West
- Callissa, Malad West
- Sankalp Heights 1-22, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bay Vue | August 2017 | December 2026 | 100% | 56 units booked out of 113 units for sale |
| Callissa | August 2017 | December 2029 | 0% | 20 units booked out of total 101 units |
| Sankalp Heights 1-22 | July 2017 | June 2024 | 100% | – |
About this project
Scorpio by Jasani Realty PvtLtd is a 139-unit BMC-sanctioned project in Malad West, Mumbai 400095, launched in August 2017 with possession due in December 2025. 42 units booked out of total 139 units. The concrete structure (RCC) is 85% complete.
Read full summary
Scorpio is a BMC-sanctioned project by Jasani Realty PvtLtd in Malad West, Mumbai 400095, registered with MahaRERA as P51800010230. It was launched in August 2017. It has 139 units in 1 building: 126 homes (2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 85% complete, final finishes 15% complete.
42 units booked out of total 139 units (30%).