Callissa, Malad West

by Rambhia Properties Private Limited · Malad West, Mumbai 400095 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 6 yrs
Concrete structure
0%Early stage
Booked
20 of 10120%
Buildings
11.5 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
60
2 BHK
20
3 BHK
21
Total units
101
Buildings
1
Land
1.5 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 60%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%20
100%0%0%20
60%0%0%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400095

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400095
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths5 yrs 11 mths
Possession date extendedBy 6 yrs3 of 3
Possession date (MahaRERA)Dec 2029Dec 2025
Concrete structure (RCC)0%100%
MahaRERA complaints (filed by or against the builder)40

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Callissa by Rambhia Properties Private Limited is a 101-unit BMC-sanctioned project in Malad West, Mumbai 400095, launched in August 2017 with possession due in December 2029. 20 units booked out of total 101 units. Work on the concrete structure (RCC) has not started.

Read full summary

Callissa is a BMC-sanctioned project by Rambhia Properties Private Limited in Malad West, Mumbai 400095, registered with MahaRERA as P51800008237. It was launched in August 2017. It has 101 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 6 years from the original December 2023. Construction: excavation complete, structure (RCC) not started, final finishes not started.

20 units booked out of total 101 units (20%).