Skip to main content

Kumbh Building, Vile Parle East

Ready to moveLapsed

by Shreeji Associates · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20174 yrs 4 mths promised
Possession (MahaRERA)
Dec 2021Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
29 of 3194%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
29
Other units
2
Total units
31
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%29
100%100%90%–
100%100%90%–
100%100%90%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths2 yrs 8 mths
Possession date extendedNo4 of 6
Possession date (MahaRERA)Dec 2021May 2022
Concrete structure (RCC)100%76%
Units booked94%71%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Kumbh Building by Shreeji Associates is a 31-unit project in Vile Parle East, Mumbai 400057, launched in August 2017; its MahaRERA registration has lapsed. 29 units booked out of total 31 units. The concrete structure (RCC) is complete.

Read full summary

Kumbh Building is a project by Shreeji Associates in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800002931. It was launched in August 2017. It has 31 units in 1 building: 29 homes (1 RK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

29 units booked out of total 31 units (94%).