Pujari Niwas, Vile Parle East

Ready to moveLapsed

by Neel Rutu Developers · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 201710 mths promised
Possession (MahaRERA)
Jun 2018Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
17
1 BHK
9
2 BHK
1
3 BHK
4
Other units
3
Total units
34
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 93%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%–
100%100%93%–
100%100%93%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)10 mths3 yrs 8 mths
Possession date extendedNo4 of 6
Possession date (MahaRERA)Jun 2018Dec 2022
Concrete structure (RCC)100%76%
Units booked–81%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pujari Niwas by Neel Rutu Developers is a 34-unit project in Vile Parle East, Mumbai 400057, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Pujari Niwas is a project by Neel Rutu Developers in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800006028. It was launched in August 2017. It has 34 units in 1 building: 31 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2018. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.