Kavya Residency, Vile Parle East

Lapsed

by Pragati Infrasquare LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20172 yrs 4 mths promised
Possession (MahaRERA)
Dec 2019Not extendedWhat does Lapsed mean?
Concrete structure
40%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
31
Total units
31
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 40%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%–
100%40%0%–
100%40%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 8 mths
Possession date extendedNo4 of 6
Possession date (MahaRERA)Dec 2019Dec 2022
Concrete structure (RCC)40%96%
Units booked–81%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Kavya Residency by Pragati Infrasquare LLP is a 31-unit project in Vile Parle East, Mumbai 400057, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 40% complete.

Read full summary

Kavya Residency is a project by Pragati Infrasquare LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800010105. It was launched in August 2017. It has 31 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2019. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.