Neev Galaxy, Malad East

Lapsed

by Neev Infrastructure Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Sep 2025Extended by 6 yrs 9 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
13 of 1872%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
11
2 BHK
7
Total units
18
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%13
100%100%60%–
100%100%60%–
100%100%60%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400097

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths3 yrs 7 mths
Possession date extendedBy 6 yrs 9 mths4 of 4
Possession date (MahaRERA)Sep 2025Dec 2025
Concrete structure (RCC)100%36%
Units booked72%47%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Neev Galaxy by Neev Infrastructure Pvt Ltd is an 18-unit project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. 13 units booked out of total 18 units. The concrete structure (RCC) is complete.

Read full summary

Neev Galaxy is a project by Neev Infrastructure Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800003057. It was launched in August 2017. It has 18 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2025, after an extension of 6 years 9 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

13 units booked out of total 18 units (72%). Since the July 2026 update, the possession date has moved from December 2019 to September 2025.