Sheetal Vaibhav Kutir, Malad East

Lapsed

by D.G.Land Developers Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Jul 20176 yrs originally promised
Possession (MahaRERA)
Dec 2025Extended by 2 yrs 5 mthsWhat does Lapsed mean?
Concrete structure
13%Mid-construction
Booked
21 of 4547%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
17
2 BHK
1
3 BHK
20
Other units
6
Total units
45
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)13%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 13%Dec 2025: Concrete structure (RCC) 13%Jul 2026: Concrete structure (RCC) 13%Oct 2026: Concrete structure (RCC) 13%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 13%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%13%0%21
100%13%0%–
100%13%0%–
100%13%0%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400097

Projects with 10–80 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs5 yrs 11 mths
Possession date extendedBy 2 yrs 5 mths2 of 3
Possession date (MahaRERA)Dec 2025Sep 2025
Concrete structure (RCC)13%23%
MahaRERA complaints (filed by or against the builder)02

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sheetal Vaibhav Kutir by D.G.Land Developers Pvt Ltd is a 45-unit project in Malad East, Mumbai 400097, launched in July 2017; its MahaRERA registration has lapsed. 21 units booked out of total 45 units. The concrete structure (RCC) is 13% complete.

Read full summary

Sheetal Vaibhav Kutir is a project by D.G.Land Developers Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800002084. It was launched in July 2017. It has 45 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 2 years 5 months from the original July 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 13% complete, final finishes not started.

21 units booked out of total 45 units (47%).