- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 6 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 26 of 3379% · 25 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 3
- 2 BHK
- 28
- Other units
- 2
- Total units
- 33
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 45% | 26 | |
| 100% | 100% | 0% | 25 | |
| 100% | 100% | 0% | 25 | |
| 100% | 100% | 0% | 23 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 3 yrs 7 mths |
| Possession date extended | By 6 yrs 6 mths | 6 of 6 |
| Possession date (MahaRERA) | Jun 2026 | Nov 2025 |
| Concrete structure (RCC) | 100% | 58% |
| Units booked | 79% | 72% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shree Sambhav Darshan CHS, Malad East
- Vinayak Tower, Malad East
- Sheetal Heights, Malad East
- Sanskruti Building No 2 C Wing, Malad East
- Maharshi Heights, Malad East
- Neev Galaxy, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Sambhav Darshan CHS | August 2017 | December 2025 | 0% | 10 units booked out of total 32 units |
| Vinayak Tower | August 2017 | June 2023 | 60% | – |
| Sheetal Heights | August 2017 | December 2021 | 10% | 35 units booked out of total 37 units |
| Sanskruti Building No 2 C Wing | August 2017 | December 2026 | 100% | 13 units booked out of 16 units for sale |
| Maharshi Heights | August 2017 | December 2028 | 56% | 3 units booked out of total 42 units |
| Neev Galaxy | August 2017 | September 2025 | 100% | 13 units booked out of total 18 units |
About this project
Crystal Pride by Crystal Construction Company is a 33-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. 26 units booked out of total 33 units. The concrete structure (RCC) is complete.
Read full summary
Crystal Pride is an SRA-sanctioned project by Crystal Construction Company in Malad East, Mumbai 400097, registered with MahaRERA as P51800009735. It was launched in August 2017. It has 33 units in 1 building: 31 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 6 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.
26 units booked out of total 33 units (79%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from June 2023 to June 2026.