Krishvi Residency, Chembur

by Shagun Chembur (Aop) · Chembur, Mumbai 400071 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
24 of 3177%
Buildings
10.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
22
4 BHK
9
Total units
31
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%24
100%100%75%–
100%100%75%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 8 mths
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2020Mar 2025
Concrete structure (RCC)100%92%
Units booked77%83%
MahaRERA complaints (filed by or against the builder)22

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Krishvi Residency by Shagun Chembur (Aop) is a 31-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017 with possession due in December 2020. 24 units booked out of total 31 units. The concrete structure (RCC) is complete.

Read full summary

Krishvi Residency is a BMC-sanctioned project by Shagun Chembur (Aop) in Chembur, Mumbai 400071, registered with MahaRERA as P51800003291. It was launched in August 2017. It has 31 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

24 units booked out of total 31 units (77%).