Shubham Trident - Sundew, Sunrise and Sunglow, Chembur

Lapsed

by Shubham Homes and Contractors Pvt Ltd · Chembur, Mumbai 400071 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
34
3 BHK
2
4 BHK
7
Total units
43
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services83%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 83%Dec 2025: Final finishes 83%Jul 2026: Final finishes 83%Excavation 100%Concrete structure (RCC) 100%Final finishes 83%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%83%–
100%100%83%–
100%100%83%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths2 yrs 8 mths
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2024Sep 2025
Concrete structure (RCC)100%100%
Units booked–90%
MahaRERA complaints (filed by or against the builder)02

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shubham Trident - Sundew, Sunrise and Sunglow by Shubham Homes and Contractors Pvt Ltd is a 43-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Shubham Trident - Sundew, Sunrise and Sunglow is a BMC-sanctioned project by Shubham Homes and Contractors Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800008658. It was launched in August 2017. It has 43 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 83% complete.