Amaltas Residency, Chembur

Lapsed

by Tattva & Mittal Corporation Pvt Ltd · Chembur, Mumbai 400071 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 5 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
29 of 3194%
Buildings
10.3 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
20
3 BHK
11
Total units
31
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 40%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%29
100%100%40%–
100%100%40%–
100%100%40%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 8 mths
Possession date extendedBy 5 yrs 6 mths6 of 6
Possession date (MahaRERA)Jun 2025Dec 2024
Concrete structure (RCC)100%92%
Units booked94%79%
MahaRERA complaints (filed by or against the builder)41

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Amaltas Residency by Tattva & Mittal Corporation Pvt Ltd is a 31-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 29 units booked out of total 31 units. The concrete structure (RCC) is complete.

Read full summary

Amaltas Residency is a BMC-sanctioned project by Tattva & Mittal Corporation Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800010534. It was launched in August 2017. It has 31 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 5 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

29 units booked out of total 31 units (94%).