Atharva, Chembur

by Maya Developers · Chembur, Mumbai 400071 · Map

Launched
Aug 20173 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2025Extended by 5 yrs 3 mths
Concrete structure
85%Mid-construction
Booked (free sale)
27 of 3479% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale27 booked out of 34 units

Rehab12 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

2 BHK
40
Other units
6
Total units
46
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 85%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%70%27
100%100%100%–
100%100%100%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth2 yrs 4 mths
Possession date extendedBy 5 yrs 3 mths6 of 6
Possession date (MahaRERA)Dec 2025Mar 2025
Concrete structure (RCC)85%100%
Units booked (free sale)79%96%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Atharva by Maya Developers is a 46-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017 with possession due in December 2025. 27 units booked out of 34 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Atharva is a BMC-sanctioned project by Maya Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800005146. It was launched in August 2017. It has 46 units in 1 building: 40 homes (2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 34 are for sale and 12 are rehab units for existing members.

Possession was due in December 2025, after an extension of 5 years 3 months from the original September 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 85% complete, final finishes 70% complete.

27 units booked out of 34 units for sale (79%).