Bhoomi Samarth, Goregaon East
Lapsed
by Samarth Erectors & Developers · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 2017First of 3 phases
- Possession (MahaRERA)
- Dec 2021 – Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 97%Weighted across 3 phases
- Booked
- –
- Buildings
- 30.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 256
- 2 BHK
- 24
- Other units
- 5
- Total units
- 285
- Buildings
- 3
- Land
- 0.1 acres
- Phases
- 3
- MahaRERA complaints
- 1
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Bhoomi Samarth A Wing Mid-construction Lapsed | P51800011356 | 86 | 91% | – | |
| Bhoomi Samarth B Wing Completed | P51800026289 | 96 | 100% | – | |
| Bhoomi Samarth C Wing Nearing possession Lapsed | P51800026826 | 98 | 100% | – |
Show updates by phase
Bhoomi Samarth A Wing (P51800011356)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 91% | 25% | – | |
| 100% | 91% | 25% | – | |
| 100% | 91% | 25% | 77 |
"–" means MahaRERA shows no figure for that update.
Bhoomi Samarth B Wing (P51800026289)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 39 |
"–" means MahaRERA shows no figure for that update.
Bhoomi Samarth C Wing (P51800026826)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 96 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400063
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 6 yrs 4 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Dec 2021 – Jun 2025 | Apr 2027 |
| Concrete structure (RCC) | 97% | 100% |
| Units booked | – | 90% |
| MahaRERA complaints (filed by or against the builder) | 1 | 14 |
The 3 projects
- Avant Hillway, Goregaon East
- Delta House, Goregaon East
- Samarth Tanish, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avant Hillway | August 2017 | Apr 2027 | 33% | 132 units booked out of 146 units for sale |
| Delta House | August 2017 | June 2026 | 100% | 151 units booked out of total 177 units |
| Samarth Tanish | August 2017 | April 2027 | 100% | 133 units booked out of total 133 units |
About this project
Bhoomi Samarth by Samarth Erectors & Developers is a 285-unit project in Goregaon East, Mumbai 400063, registered with MahaRERA in 3 phases, with possession dates from December 2021 to June 2025. The concrete structure (RCC) is 97% complete.
Read full summary
Bhoomi Samarth is a project by Samarth Erectors & Developers in Goregaon East, Mumbai 400063, registered with MahaRERA as 3 phases (P51800011356, P51800026289, P51800026826). The first phase was launched in August 2017. Together the phases have 285 units in 3 buildings: 280 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 2 are lapsed and 1 is completed.
The phases' registered possession dates run from December 2021 to June 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 97% complete and final finishes 8% complete. 2 of the 3 phases have their structure complete.