Skip to main content

Bhoomi Samarth, Goregaon East

Lapsed

by Samarth Erectors & Developers · Goregaon East, Mumbai 400063 · Map

Launched
Aug 2017First of 3 phases
Possession (MahaRERA)
Dec 2021 – Jun 2025Not extendedWhat does Lapsed mean?
Concrete structure
97%Weighted across 3 phases
Booked
–
Buildings
30.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
256
2 BHK
24
Other units
5
Total units
285
Buildings
3
Land
0.1 acres
Phases
3
MahaRERA complaints
1

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Bhoomi Samarth A Wing
Mid-construction Lapsed
P518000113568691%–
Bhoomi Samarth B Wing
Completed
P5180002628996100%–
Bhoomi Samarth C Wing
Nearing possession Lapsed
P5180002682698100%–
Show updates by phase

Bhoomi Samarth A Wing (P51800011356)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%25%–
100%91%25%–
100%91%25%77

"–" means MahaRERA shows no figure for that update.

Bhoomi Samarth B Wing (P51800026289)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%–
100%100%0%–
100%100%0%39

"–" means MahaRERA shows no figure for that update.

Bhoomi Samarth C Wing (P51800026826)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%–
100%100%0%–
100%100%0%96

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)97%
Finishes, lifts and services8%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 97%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 97%Dec 2024: Final finishes 8%Dec 2025: Final finishes 8%Jul 2026: Final finishes 8%Excavation 100%Concrete structure (RCC) 97%Final finishes 8%

How to read construction stages

Compared with 3 similar projects in PIN 400063

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths6 yrs 4 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Dec 2021 – Jun 2025Apr 2027
Concrete structure (RCC)97%100%
Units booked–90%
MahaRERA complaints (filed by or against the builder)114

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Bhoomi Samarth by Samarth Erectors & Developers is a 285-unit project in Goregaon East, Mumbai 400063, registered with MahaRERA in 3 phases, with possession dates from December 2021 to June 2025. The concrete structure (RCC) is 97% complete.

Read full summary

Bhoomi Samarth is a project by Samarth Erectors & Developers in Goregaon East, Mumbai 400063, registered with MahaRERA as 3 phases (P51800011356, P51800026289, P51800026826). The first phase was launched in August 2017. Together the phases have 285 units in 3 buildings: 280 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 2 are lapsed and 1 is completed.

The phases' registered possession dates run from December 2021 to June 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 97% complete and final finishes 8% complete. 2 of the 3 phases have their structure complete.