Shiv Aaradhana, Borivali East

Ready to move

by Brightmen Buildspaces LLP · Borivali East, Mumbai 400066 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 3 yrs 4 mths
Concrete structure
100%Ready to move
Booked (free sale)
56 of 6488% · 21 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale56 booked out of 64 units

Rehab21 units for existing members

Total 85 units. Rehab units are not for sale.

Project facts

1 BHK
42
2 BHK
43
Total units
85
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
64
Rehab units
21
Reserved units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 0%Jul 2026: Excavation 10%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 86%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 45%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%56
10%86%45%55
0%0%0%54
100%70%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 3 yrs 4 mths6 of 6
Possession date (MahaRERA)Apr 2027Sep 2026
Concrete structure (RCC)100%87%
Units booked (free sale)88%96%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Aaradhana by Brightmen Buildspaces LLP is an 85-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in April 2027. 56 units booked out of 64 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shiv Aaradhana is a BMC-sanctioned project by Brightmen Buildspaces LLP in Borivali East, Mumbai 400066, registered with MahaRERA as P51800003581. It was launched in August 2017. It has 85 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 85 units, 64 are for sale and 21 are rehab units for existing members.

Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

56 units booked out of 64 units for sale (88%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 86% to 100% and the possession date has moved from December 2025 to April 2027.