Ekta Apartment Upto 17th Floor, Borivali East
Lapsed
by Aditya Enterprise Project Ekta · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20171 yr 7 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 7 yrs 3 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 71 of 7299%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 31
- 3 BHK
- 33
- Other units
- 7
- Total units
- 72
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 100% | 60% | 71 | |
| 95% | 100% | 60% | – | |
| 95% | 100% | 60% | – | |
| 95% | 100% | 60% | 71 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 7 mths | 4 yrs 10 mths |
| Possession date extended | By 7 yrs 3 mths | 6 of 6 |
| Possession date (MahaRERA) | Jun 2026 | Jun 2026 |
| Concrete structure (RCC) | 100% | 87% |
| Units booked | 99% | 96% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Park Residency, Borivali East
- Rooprajat Enclave, Borivali East
- Shiv Aaradhana, Borivali East
- Navkar Heights, Borivali East
- Mayur Pankh Chs Ltd, Borivali East
- Vklal Hari Phase I, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Park Residency | August 2017 | December 2021 | 67% | – |
| Rooprajat Enclave | August 2017 | April 2027 | 74% | 63 units booked out of 64 units for sale |
| Shiv Aaradhana | August 2017 | April 2027 | 100% | 56 units booked out of 64 units for sale |
| Navkar Heights | August 2017 | December 2023 | 0% | 35 units booked out of total 36 units |
| Mayur Pankh Chs Ltd | August 2017 | December 2025 | 100% | 40 units booked out of total 56 units |
| Vklal Hari Phase I | August 2017 | December 2026 | 100% | 93 units booked out of total 97 units |
About this project
Ekta Apartment Upto 17th Floor by Aditya Enterprise Project Ekta is a 72-unit MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017; its MahaRERA registration has lapsed. 71 units booked out of total 72 units. The concrete structure (RCC) is complete.
Read full summary
Ekta Apartment Upto 17th Floor is a MHADA-sanctioned project by Aditya Enterprise Project Ekta in Borivali East, Mumbai 400066, registered with MahaRERA as P51800009361. It was launched in August 2017. It has 72 units in 1 building: 65 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 7 years 3 months from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) complete, final finishes 60% complete.
71 units booked out of total 72 units (99%).