Vklal Hari Phase I, Borivali East

by Veekaylal Investment Company Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Aug 20178 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
93 of 9796% · 88 in Jul 2026
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
97
Total units
97
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%93
100%100%10%88
100%100%0%86
100%100%0%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)8 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2026Sep 2026
Concrete structure (RCC)100%87%
Units booked96%88%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vklal Hari Phase I by Veekaylal Investment Company Private Limited is a 97-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in December 2026. 93 units booked out of total 97 units. The concrete structure (RCC) is complete.

Read full summary

Vklal Hari Phase I is an SRA-sanctioned project by Veekaylal Investment Company Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800010657. It was launched in August 2017. It has 97 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

93 units booked out of total 97 units (96%). Since the July 2026 update, 5 more units have been booked.