Rooprajat Enclave, Borivali East

by Siddhivinayak Developers · Borivali East, Mumbai 400066 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 5 yrs 4 mths
Concrete structure
74%Mid-construction
Booked (free sale)
63 of 6498% · 9 rehab units
Buildings
20.5 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale63 booked out of 64 units

Rehab9 units for existing members

Land-owner share7 units, not for sale

Total 80 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
1
1 BHK
35
2 BHK
34
Other units
10
Total units
80
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
19
Free-sale units
64
Rehab units
9
Land-owner share (not for sale)
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)74%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 74%Dec 2025: Concrete structure (RCC) 74%Jul 2026: Concrete structure (RCC) 74%Oct 2026: Concrete structure (RCC) 74%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 74%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%74%50%63
100%74%50%63
100%74%50%63
100%74%50%54

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths4 yrs 10 mths
Possession date extendedBy 5 yrs 4 mths6 of 6
Possession date (MahaRERA)Apr 2027Sep 2026
Concrete structure (RCC)74%100%
Units booked (free sale)98%88%
MahaRERA complaints (filed by or against the builder)191

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rooprajat Enclave by Siddhivinayak Developers is an 80-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in April 2027. 63 units booked out of 64 units for sale. The concrete structure (RCC) is 74% complete.

Read full summary

Rooprajat Enclave is an SRA-sanctioned project by Siddhivinayak Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800004097. It was launched in August 2017. It has 80 units in 2 buildings: 70 homes (1 RK, 1 BHK and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 80 units, 64 are for sale, 9 are rehab units for existing members and 7 are the land-owner's share, not for sale.

Its registered possession date is April 2027, extended by 5 years 4 months from the original December 2021. Construction: excavation complete, structure (RCC) 74% complete, final finishes 50% complete.

63 units booked out of 64 units for sale (98%).